I don't think so - all I did was display the successor column, set the table definition to have the attribute style of 'unique task ID' and then did a simple highlight text>copy and pasted these values in the successor cell of the new task that I wanted to have the same links.
Just checked our support call system and I see you have also had a conversation with our analysts on this one, so hopefully they have reinforced the advice.
Cheers,
Ben
Member for
18 years 5 months
Member for18 years5 months
Submitted by Chris Lothian on Fri, 2015-06-19 13:19
I'd already tried this (as I knew that's how it worked in MS Project), but couldn't get it to work for me. Were there any other settings that you changed too?
There may be a better way, but what comes to mind first is to display the relevant successor/predecessor column and simply copy/paste the data in the cells between the two tasks. I just tried this and it worked - needed to set it to show Unique Task ID in Table Definition rather than Task Name to make it clearer.
Member for
13 years 9 monthsHi Chris,I don't think so -
Hi Chris,
I don't think so - all I did was display the successor column, set the table definition to have the attribute style of 'unique task ID' and then did a simple highlight text>copy and pasted these values in the successor cell of the new task that I wanted to have the same links.
Just checked our support call system and I see you have also had a conversation with our analysts on this one, so hopefully they have reinforced the advice.
Cheers,
Ben
Member for
18 years 5 monthsThanks for response Ben. I'd
Thanks for response Ben.
I'd already tried this (as I knew that's how it worked in MS Project), but couldn't get it to work for me. Were there any other settings that you changed too?
Chris
Member for
13 years 9 monthsHi Chris,There may be a
Hi Chris,
There may be a better way, but what comes to mind first is to display the relevant successor/predecessor column and simply copy/paste the data in the cells between the two tasks. I just tried this and it worked - needed to set it to show Unique Task ID in Table Definition rather than Task Name to make it clearer.
Ben @ Asta