Primavera Project Planner - P3 Member for 20 years 7 months Member for 20 years 7 months Submitted by Anand Kulkarni on Tue, 2005-04-05 00:36 Permalink RE: Installed Quantity for physical % complete Dear Wan, Yes Planned quantities are the budgeted quantities only. Yes the report gives you resource wise break-up for all the activities with the summary of resources. Multiples resoures to one activitiy is not an issue at all. cheers anand Member for 20 years 7 months Member for 20 years 8 months Submitted by Dylan Wan, PMP EVP on Mon, 2005-04-04 15:11 Permalink RE: Installed Quantity for physical % complete Thanks for your reply, Anand. Is the planned quantity entered as budgeted quantity in the resource window? Can I have an activity level quantity? We have multiple resources assigned to the same activity. Member for 20 years 7 months Member for 20 years 7 months Submitted by Anand Kulkarni on Mon, 2005-04-04 09:19 Permalink RE: Installed Quantity for physical % complete Hi Wan, In Tools/Tabular Reports/Resource/Earned Value The out put is detailed Resource wise % complete Actual Qty. of Work Performed (ACP), Budgeted qty. of Work Scheduled (BCWP), Budgeted qty. of work scheduled(BCWS, Variance & At completion quantities cheers, Anand Log in or register to post comments
Member for 20 years 7 months Member for 20 years 7 months Submitted by Anand Kulkarni on Tue, 2005-04-05 00:36 Permalink RE: Installed Quantity for physical % complete Dear Wan, Yes Planned quantities are the budgeted quantities only. Yes the report gives you resource wise break-up for all the activities with the summary of resources. Multiples resoures to one activitiy is not an issue at all. cheers anand
Member for 20 years 7 months Member for 20 years 8 months Submitted by Dylan Wan, PMP EVP on Mon, 2005-04-04 15:11 Permalink RE: Installed Quantity for physical % complete Thanks for your reply, Anand. Is the planned quantity entered as budgeted quantity in the resource window? Can I have an activity level quantity? We have multiple resources assigned to the same activity.
Member for 20 years 7 months Member for 20 years 7 months Submitted by Anand Kulkarni on Mon, 2005-04-04 09:19 Permalink RE: Installed Quantity for physical % complete Hi Wan, In Tools/Tabular Reports/Resource/Earned Value The out put is detailed Resource wise % complete Actual Qty. of Work Performed (ACP), Budgeted qty. of Work Scheduled (BCWP), Budgeted qty. of work scheduled(BCWS, Variance & At completion quantities cheers, Anand
Member for
20 years 7 monthsRE: Installed Quantity for physical % complete
Dear Wan,
Yes Planned quantities are the budgeted quantities only.
Yes the report gives you resource wise break-up for all the activities with the summary of resources.
Multiples resoures to one activitiy is not an issue at all.
cheers
anand
Member for
20 years 7 monthsRE: Installed Quantity for physical % complete
Thanks for your reply, Anand.
Is the planned quantity entered as budgeted quantity in the resource window?
Can I have an activity level quantity? We have multiple resources assigned to the same activity.
Member for
20 years 7 monthsRE: Installed Quantity for physical % complete
Hi Wan,
In Tools/Tabular Reports/Resource/Earned Value
The out put is detailed Resource wise % complete Actual Qty. of Work Performed (ACP), Budgeted qty. of Work Scheduled (BCWP), Budgeted qty. of work scheduled(BCWS, Variance & At completion quantities
cheers,
Anand