Installed Quantity for physical % complete

Member for

20 years 7 months

Dear Wan,



Yes Planned quantities are the budgeted quantities only.



Yes the report gives you resource wise break-up for all the activities with the summary of resources.



Multiples resoures to one activitiy is not an issue at all.





cheers



anand

Member for

20 years 7 months

Thanks for your reply, Anand.



Is the planned quantity entered as budgeted quantity in the resource window?



Can I have an activity level quantity? We have multiple resources assigned to the same activity.

Member for

20 years 7 months

Hi Wan,



In Tools/Tabular Reports/Resource/Earned Value



The out put is detailed Resource wise % complete Actual Qty. of Work Performed (ACP), Budgeted qty. of Work Scheduled (BCWP), Budgeted qty. of work scheduled(BCWS, Variance & At completion quantities



cheers,



Anand