Planned / Actual % Complete S-Curve

Member for

11 years 1 month

I don't want  to show any cost allocation etc, just a basic planned % complete vs actual % complete line over the project duration.

Member for

19 years 10 months

Hi Ryan

This is too big a topic for exchange here.

Go to Help and search on Histograms.

Select "Introduction to Histograms" and start from there.

Best regards

Mike Testro

Member for

11 years 1 month

Hi Mike,

 

Thanks for your response, but I'm struggling a little here.



Any chance you can help me with a walkthrough of what I'm meant to do?

 

This is the first histogram I've ever done and haven't a clue...



Kind regards,



Ryan

Member for

19 years 10 months

Hi Ryan

Asta software will do this for you.

Create a histogram with the selected data.

Right click the histogram and select S-Curve - the graph will be created in Excell.

Best regards

Mike Testro