Hi Ronron

You should claim for the work and materials procured prior to the cancellation.

Best regards

Mike Testro

Member for

15 years 11 months

Dear Mike,

Thank for the reply,

THe omission of work was the underground piping it was cancelled by client. however we had procure the material and install few die-inch. anyway to claim this omission of work.

Regards

Member for

19 years 10 months

Hi Ronron

I need a bit of clarification.

Was the work actually installed before the omission?

Best regards