How to generate S-curve for physical progress where work consist of different units

Member for

21 years 9 months

Hi Anil,

I understand your problem.

Use weighted value of each work package as suggested by Daniel. You can get the weighted values from the client.

You should get something like this, so that the weightings total to 100%. 

S#Work PackageWeighted Value (%)1Sewer Line20%2Lay Pipe45%3Sewer Connection5%4Manhole Chambers10%5Chamber Inspections10%6Pump Stations10% Total100%

 With this, you should be able to set-up s-curve for physical progress measurement. I'm assuming you have your physical progress rules of credit (progress metrics) already defined.

=jerome

Member for

14 years 2 months

Hi Mr. jerome

Thank you for your valuable input.

However there is probelm in cost. The proejct is done by different contractors and we are a PMC by the client.

So thay don't give any information about cost in schedule. only the monthly billing schedule.

So Is there any other way we can do may be using actual work.

thank you

Anil

Member for

24 years

Hi Jerome,

In addition to cost, You can use Manhours or Mandays or weighted value for each element of work.

 

Regards,

Daniel

Member for

21 years 9 months

Hi Anil,

You should be able to generate s-curve for the entire project but you'll need a common unit of measurement for the different work scopes.

Have you considered using cost as your common denominator? Your different work scopes will have cost estimates that you can use.

 

=jerome