Alexandre,

What is pseudo"hammock?

Could you explain more?

Best

Member for

22 years 9 months

Vaibhav,

MS project does not know what a hammock task is; therefore, il you want to simulate a hammock task in MS Project, you have to copy and paste "paste special with a link" the start date of the predecessor milestone and the successor milestone with the "hammock"

Member for

10 years 8 months

Dear Mountaz, wht is pseudo hammock ?

Member for

22 years 9 months

Mountaz,

not very easy with MS Project; you could try as follows:

1. create "pseudo"hammock tasks whose predecessors and successors are milestones with date constraints at the beginning and end of each month

2. using the Cost field in the Task sheet, enter the monthly amount of salaries you mention

Good luck,

Alexandre