MS project does not know what a hammock task is; therefore, il you want to simulate a hammock task in MS Project, you have to copy and paste "paste special with a link" the start date of the predecessor milestone and the successor milestone with the "hammock"
Member for
10 years 8 months
Member for10 years8 months
Submitted by vaibhavpaydelwar on Tue, 2015-02-17 09:56
Member for
21 years 10 monthsAlexandre,What is
Alexandre,
What is pseudo"hammock?
Could you explain more?
Best
Member for
22 years 9 monthsVaibhav,MS project does not
Vaibhav,
MS project does not know what a hammock task is; therefore, il you want to simulate a hammock task in MS Project, you have to copy and paste "paste special with a link" the start date of the predecessor milestone and the successor milestone with the "hammock"
Member for
10 years 8 monthsDear Mountaz, wht is pseudo
Dear Mountaz, wht is pseudo hammock ?
Member for
22 years 9 monthsMountaz,not very easy with MS
Mountaz,
not very easy with MS Project; you could try as follows:
1. create "pseudo"hammock tasks whose predecessors and successors are milestones with date constraints at the beginning and end of each month
2. using the Cost field in the Task sheet, enter the monthly amount of salaries you mention
Good luck,
Alexandre