In FF case, the successor task will be planned to start latest possible. Task A= 10 days, Task B=2 days. Defining B as successor to A with FF relationship, will plan B to start on day 8, which is not very favorable.
Am I right?
Nozar
Member for
23 years
Member for23 years
Submitted by Steven Oliver on Tue, 2005-03-22 10:56
Member for
23 yearsRE: RE:
It should start on day 9 (i.e a 2 day task will occupy days 9&10 to finish coincident with a 10 day activity.
What makes you think that this would be unfavourable ?
Member for
21 years 3 monthsRE: RE:
Hey Steven,
Thanks for your response.
In FF case, the successor task will be planned to start latest possible. Task A= 10 days, Task B=2 days. Defining B as successor to A with FF relationship, will plan B to start on day 8, which is not very favorable.
Am I right?
Nozar
Member for
23 yearsRE:
My preference would be FF, as the start of the successor is then dicated by the progress of the predecessor.