Oracle Primavera - PM6 Member for 22 years 6 months Member for 22 years 6 months Submitted by Mirza Imam Baig on Mon, 2005-03-28 14:22 Permalink RE: Exporting from P3 e/c to P3 Hi friends, Thanks for the response Member for 20 years 9 months Member for 20 years 9 months Submitted by Alan Callow on Mon, 2005-03-21 04:39 Permalink RE: Exporting from P3 e/c to P3 Under Admin > Admin Preferences > Time periods > check the default time this may affect duration unless shown in hours Member for 21 years 3 months Member for 21 years 3 months Submitted by Henk van der Heide on Sun, 2005-03-20 18:29 Permalink RE: Exporting from P3 e/c to P3 Imam, I think youve a calender problem Best way to find out: Check both durations in Hours. It seems that 1 day is not always 8 hours work. (this can be the problem). Regards Henk Log in or register to post comments
Member for 22 years 6 months Member for 22 years 6 months Submitted by Mirza Imam Baig on Mon, 2005-03-28 14:22 Permalink RE: Exporting from P3 e/c to P3 Hi friends, Thanks for the response
Member for 20 years 9 months Member for 20 years 9 months Submitted by Alan Callow on Mon, 2005-03-21 04:39 Permalink RE: Exporting from P3 e/c to P3 Under Admin > Admin Preferences > Time periods > check the default time this may affect duration unless shown in hours
Member for 21 years 3 months Member for 21 years 3 months Submitted by Henk van der Heide on Sun, 2005-03-20 18:29 Permalink RE: Exporting from P3 e/c to P3 Imam, I think youve a calender problem Best way to find out: Check both durations in Hours. It seems that 1 day is not always 8 hours work. (this can be the problem). Regards Henk
Member for
22 years 6 monthsRE: Exporting from P3 e/c to P3
Hi friends,
Thanks for the response
Member for
20 years 9 monthsRE: Exporting from P3 e/c to P3
Under Admin > Admin Preferences > Time periods > check the default time this may affect duration unless shown in hours
Member for
21 years 3 monthsRE: Exporting from P3 e/c to P3
Imam,
I think youve a calender problem
Best way to find out: Check both durations in Hours.
It seems that 1 day is not always 8 hours work. (this can be the problem).
Regards
Henk