Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2014-03-22 16:03 Permalink Hi IsmaelNot really - they Hi Ismael Not really - they are both the same techniques but according to the American's TIA is for work in progress and SIA is for completed projects. Best regards Mike Testro Member for 11 years 7 months Member for 11 years 7 months Submitted by is*****@g***** on Sat, 2014-03-22 14:35 Permalink many thanks dear.can we say many thanks dear. can we say that TIA is one of the approches of SIA ? Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Wed, 2014-03-19 16:19 Permalink Hi IsmailThese are American Hi Ismail These are American titles. In the definitions section of types of analysis prepared for the Virginia Department of Transport: http://www.virginiadot.org/business/resources/const/0703_PrinciplesofSIA.pdf The terms are defined as follows: Modification Impact Analysis (U.S. Army Corps of Engineers) – a contemporaneous schedule impact analysis technique in which at the time of modification, the actual status of the job is determined, the schedule is updated, and the delay is inserted to quantify singular impact Time Impact Analysis – similar to the Modification Impact Analysis, a schedule impact analysis technique that recreates the actual status of the job at the time of modification, updates the schedule, inserts delays, and quantifies singular impact; although retrospective in that it is done after the fact, it has a contemporaneous orientation, not a hindsight perspective Schedule Impact – the potential effect of a delay or change on a project schedule; may be in the form of delay or change in project completion date, delay or change in project sequence, or consumption of float Schedule Impact Analysis (SIA) – the process of quantifying and apportioning the effect of delay or change on the project schedule. Which appears to mean that TIA is used for work in progress and SIA is forensic (or maybe not). Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sat, 2014-03-22 16:03 Permalink Hi IsmaelNot really - they Hi Ismael Not really - they are both the same techniques but according to the American's TIA is for work in progress and SIA is for completed projects. Best regards Mike Testro
Member for 11 years 7 months Member for 11 years 7 months Submitted by is*****@g***** on Sat, 2014-03-22 14:35 Permalink many thanks dear.can we say many thanks dear. can we say that TIA is one of the approches of SIA ?
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Wed, 2014-03-19 16:19 Permalink Hi IsmailThese are American Hi Ismail These are American titles. In the definitions section of types of analysis prepared for the Virginia Department of Transport: http://www.virginiadot.org/business/resources/const/0703_PrinciplesofSIA.pdf The terms are defined as follows: Modification Impact Analysis (U.S. Army Corps of Engineers) – a contemporaneous schedule impact analysis technique in which at the time of modification, the actual status of the job is determined, the schedule is updated, and the delay is inserted to quantify singular impact Time Impact Analysis – similar to the Modification Impact Analysis, a schedule impact analysis technique that recreates the actual status of the job at the time of modification, updates the schedule, inserts delays, and quantifies singular impact; although retrospective in that it is done after the fact, it has a contemporaneous orientation, not a hindsight perspective Schedule Impact – the potential effect of a delay or change on a project schedule; may be in the form of delay or change in project completion date, delay or change in project sequence, or consumption of float Schedule Impact Analysis (SIA) – the process of quantifying and apportioning the effect of delay or change on the project schedule. Which appears to mean that TIA is used for work in progress and SIA is forensic (or maybe not). Best regards Mike Testro
Member for
19 years 10 monthsHi IsmaelNot really - they
Hi Ismael
Not really - they are both the same techniques but according to the American's TIA is for work in progress and SIA is for completed projects.
Best regards
Mike Testro
Member for
11 years 7 monthsmany thanks dear.can we say
many thanks dear.
can we say that TIA is one of the approches of SIA ?
Member for
19 years 10 monthsHi IsmailThese are American
Hi Ismail
These are American titles.
In the definitions section of types of analysis prepared for the Virginia Department of Transport:
http://www.virginiadot.org/business/resources/const/0703_PrinciplesofSIA.pdf
The terms are defined as follows:
Modification Impact Analysis (U.S. Army Corps of Engineers) – a contemporaneous
schedule impact analysis technique in which at the time of modification, the
actual status of the job is determined, the schedule is updated, and the delay is
inserted to quantify singular impact
Time Impact Analysis – similar to the Modification Impact Analysis, a schedule impact
analysis technique that recreates the actual status of the job at the time of
modification, updates the schedule, inserts delays, and quantifies singular impact;
although retrospective in that it is done after the fact, it has a contemporaneous
orientation, not a hindsight perspective
Schedule Impact – the potential effect of a delay or change on a project schedule; may
be in the form of delay or change in project completion date, delay or change in
project sequence, or consumption of float
Schedule Impact Analysis (SIA) – the process of quantifying and apportioning the
effect of delay or change on the project schedule.