Summary task disappears

Member for

22 years 9 months

Thorsten,

thank you for your help; where is the "Expand Sate" tab (or field?) that you have mentionned, I cannot find it either in Tilos 8 in English or anything to be compared in Tilos 7 French

(10 mn later) : I have found the Expand State option in the Summary Task tab of the Time Distance cell properties; thanks again for your help

Alexandre

Member for

14 years 4 months

Dear Alexandre,

for a Time-Distance Cell it is possible to switch off the display of the Summary Tasks. Please check in the Tab "Expand State" of the Time-Distance-Cell, if the display of the Summary tasks is switched off.

 

regards

Thorsten