Hi Gary,

Thanks. I have done all the above instructions and still the critical path is not shown as red. Total float for critical activities are "0". So now what i have done is  - In the critical activities dialogue box, i put a value of 1 for " Total float less than" option. Now the critical path is shown in red. Not sure if its the right way. Please do reply.

Thanks a bunch for the speedy reply to my first post :)

Member for

12 years 6 months

Hi Gary,

Thanks. I have done all the above instructions and still the critical path is not shown as red. Total float for critical activities are "0". So now what i have done is  - In the critical activities dialogue box, i put a value of 1 for " Total float less than" option. Now the critical path is shown in red. Not sure if its the right way. Please do reply.

Thanks a bunch for the speedy reply to my first post :)

Member for

16 years 7 months

Right-click on the gant-chart section, and go to "Bars"

For any bars that are checked as "visible" (typically your Early Bar), make sure the "critical" option is also checked

In the botom-right of the bars window, make sure both options are checked for "show critical colours on"

In the same area, make sure the colour is red (this is the standard colour used to show critical tasks)

 

Cheers,

 

G