Hello Sir,

 

thanks for ur reply.

Ok Then is there a way to get the Planned % complete week wise for my project from MSP.

I have to show the week wise planned % of my project to my cleint one week before i start to monitor the project...
In P6 I used to change the data date(Week wise) and get the planned % complete for that week.So is there anything like this which can be done in MSP also.

Member for

24 years 6 months

The % Completes that MSP has are:

  • % Complet which is in actual fact % Duration
  • % Work Complete which may be unlinked from  % Complete
  • Physical % Complete which is a manually entered value.

For any other you will need to enter a formulae ina custom column.

 

Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

www.eastwoodharris.com

www.primavera.com.au - a Primavera scheduling software resources site