Hi Mangesh

Unless you are involved in delay analysis then a typical planner need not get too involved in contract law.

It is important that you read and understand the contract for your current project - particularly the clauses relating to programmes - notices and EoT.

From what I recall in India is that they very rarely use FIDIC in its pure form unles it is a World Bank project.

I would advise you to read the India Contract Act 1872 which has greater relevance to modern construction in India.

Best regards

Mike Testro