If the late busbar connection did in fact cause delays and not just use up float then you have reasonable grounds to claim an EoT.
Move the connection milestone to the actual date and constrain it to must start "on or after" and reschedule the programme.
This will show the calculated theoretical delay which will not necessarily reflect your EoT because the contractor must mitigate any such delay - provided it doesn't cost anything.
Member for
19 years 10 monthsHi Dwi If the late busbar
Hi Dwi
If the late busbar connection did in fact cause delays and not just use up float then you have reasonable grounds to claim an EoT.
Move the connection milestone to the actual date and constrain it to must start "on or after" and reschedule the programme.
This will show the calculated theoretical delay which will not necessarily reflect your EoT because the contractor must mitigate any such delay - provided it doesn't cost anything.
Best regards
Mike Testro