Staff Resource Planning Using ASTA

Member for

19 years 10 months

Hi Joseph

Set up a series of task hammocks that contain the scope of work for each staff resource. For instance if you are employing an MEP supervisor then add all the MEP tasks to the hammock and then add the Supervisor resource to the hammock.

The same with other trades such as Groundworks - concrete - finishings etc.

Staff that are going to be on site full time add to the project Level 1 summary.

Best regards

Mike Testro