"Must Start on Particular Day" Constraint

Member for

22 years 11 months

Thanks for the replies. I did end up setting up a calendar with Sat/Sun working, against which a predecessor task for "travel to site" is set up, which then links into the actual task (Mon-Fri working calendar) thus making sure it starts on a Monday.

Member for

21 years 8 months

Prefer to use lag calendars, no extra tasks/activities to update or hide. Just create a lag calendar working only on Sunday and use this calendar on your links with a lag of 1 hr.

Photobucket

Note that only link from activity 2 to activity 3 and activity 3 are the critical path. Activities 1 and 2 although on the longest path (easy there is just one) are not critical, longest path is not critical all the way, and this is due to pure logic, under resource leveling it gets more complicated.

A similar approach can be used when some activities must start on the week end but once started can continue during the regular week. To me the everyday use of different lag calendar occurs with concrete curing.

Sorry I do not use MSP but hope the idea on using lag calendar to control successor task is of help.

Member for

17 years 9 months

 

There is actually a quite elegant way to do this in MS Project

Create a separate calendar “MondayEarlyMorning”, with working time every Monday 00:00 – 01:00, all other times are not working.

Then, before every task, which you want to start on Monday, you should insert another task “MondayStartMilestone”. This task should have duration <=1h  and should have a calendar “MondayEarlyMorning”, assigned to it. As a consequence, the task, which will be linked to it will always start on Monday.

Member for

24 years 9 months

Tony,

I think that milestone on Mondays is the best possible solution.