Primavera Project Planner - P3 Member for 15 years 4 months Member for 15 years 4 months Submitted by impire new on Wed, 2012-05-23 09:25 Permalink Yes, it works for me.Thanks a Yes, it works for me. Thanks a lot for your kind reply. Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2012-04-16 11:03 Permalink Hello,you cannot use Hello, you cannot use "Progress Spotlight" as a filter criterion in the filter dialog, select Within Range (WR), Data Date, (Data Date + the difference between New Data Date and Data Date) for instance Early Start WR Data Date and Data Date + 20 days Alexandre Log in or register to post comments
Member for 15 years 4 months Member for 15 years 4 months Submitted by impire new on Wed, 2012-05-23 09:25 Permalink Yes, it works for me.Thanks a Yes, it works for me. Thanks a lot for your kind reply.
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2012-04-16 11:03 Permalink Hello,you cannot use Hello, you cannot use "Progress Spotlight" as a filter criterion in the filter dialog, select Within Range (WR), Data Date, (Data Date + the difference between New Data Date and Data Date) for instance Early Start WR Data Date and Data Date + 20 days Alexandre
Member for
15 years 4 monthsYes, it works for me.Thanks a
Yes, it works for me.
Thanks a lot for your kind reply.
Member for
22 years 9 monthsHello,you cannot use
Hello,
you cannot use "Progress Spotlight" as a filter criterion
in the filter dialog, select Within Range (WR), Data Date, (Data Date + the difference between New Data Date and Data Date)
for instance Early Start WR Data Date and Data Date + 20 days
Alexandre