MSP2007 - Showing Progress within Summary Bar

Member for

22 years 9 months

Tony,

when you copy the project schedule from one mpp file to another, you only copy the tasks and resources, not the barts and filters setup

therefore your new project is using the default setup you were missing in the first one

Alexandre

Member for

22 years 11 months

Alexandre,

Thanks for replying. Having had yet another look at the problem, it does seem as if it is related to one project file only - not sure why the Summary Progress will not show within the planned summary bar on this particular file, but having copied the entire content into a new file, it does now appear to be showing as I want it. Strange.....!!!!

Member for

22 years 9 months

Tony,

it works exactly the same way in MSP 2007 as in MSP 2003

be carefull to enter the same number in the "Row" column when setting up the Progress Bar on Summary Tasks; I presume you have 1 for Planned Summary and 2 for Progress Summary

Alexandre