im going to try and rephrase this as im probably not making sense, so ignore the above.......
basically i am inputting the actual data of hours in as the programme develops up against my baseline - i have allocated a certain percentage of someones time to a certain activity.
therefore there hours have been profiled on a daily basis which is great. however on the monday for example i have them baslined working for 4 hours in toal - but they actually worked 24 hours. this has now made my percentage complete as 50% but the project isnt actually that in the real world it is about 10% as this extra time they have spent was not accounted for (typical civils).
i want to cut the line between this link as my programme says they have 24 hours left however they may have 100 hours left who knows. as soon as i type in 24 hours the money has gone and the percentage complete is 100% but in reality it isnt and is still onsite. this is therefore going to show on my gant as complete when it isnt in reality?
as i mentioned above i think its the way i have set up my programme........
any input would be appreciated guys, i think i just need it breaking down as im probaly trying to manage it wrong?
Member for
13 years 9 monthsim going to try and rephrase
im going to try and rephrase this as im probably not making sense, so ignore the above.......
basically i am inputting the actual data of hours in as the programme develops up against my baseline - i have allocated a certain percentage of someones time to a certain activity.
therefore there hours have been profiled on a daily basis which is great. however on the monday for example i have them baslined working for 4 hours in toal - but they actually worked 24 hours. this has now made my percentage complete as 50% but the project isnt actually that in the real world it is about 10% as this extra time they have spent was not accounted for (typical civils).
i want to cut the line between this link as my programme says they have 24 hours left however they may have 100 hours left who knows. as soon as i type in 24 hours the money has gone and the percentage complete is 100% but in reality it isnt and is still onsite. this is therefore going to show on my gant as complete when it isnt in reality?
as i mentioned above i think its the way i have set up my programme........
any input would be appreciated guys, i think i just need it breaking down as im probaly trying to manage it wrong?
thanks
steve