Primavera Contractor

Member for

16 years 7 months

The only workaround I can think of is to setup an activity code, and copy the AID of just the section you want sorted differently over to it.

Then you should be able set up a two-level Sort from "View" > "Group and Sort" > "Sort" 

First sort by the activity code, then by date

 

Cheers,

 

G

Member for

15 years 2 months

That has worked thanks, heres another one for you.....

 

when you click on the cells at the top of the gantt chart you change the ordering of that cell, eg. order it by ID number or by date - but this is only for the entire programme.

 

Is there a way to only order certain sections, eg I want to order the entire programme via date except for one section I want to order via the ID?

 

Any ideas?

Member for

16 years 7 months

Tony,

 

I haven't used Contractor, but this sounds very similar to how P6 works so I shall assume it's the same approach.

In P6, you can only show relationships between either baseline or current bars -not both.

To change from showing baseline relationships to current relationships, got to "View" > "bars", and shift the baseline bar down to the bottom of the list of visible bars.

 

Cheers,

 

G