Durations

Member for

13 years 11 months

 Hi Mike,

             sorry I took so long getting back her. You were right, everything pretty much went to plan afeter I got the calanders sorted out.

 

Craig

Member for

19 years 10 months

Hi Craig

Welcome to Planning Planet

With such a broad programme it is almost inevitable that the original estimated durations will have nothing to do with reality - so don't take them as correct.

Your problem is most likely calendar related.

Check that your duration column is formatted to working days if your calendar is set to working days.

Best regards

Mike Testro