Shortly. flags are similar to milestones in that they are also zero duration activities and they flag either the start or completion of an activity or group of activities.
Flags however can only have a predecessor, but no successor activities and thus have no impact on your schedule. Flags do not need to be updated but are automatically completed when their predecessors are completed.
A flag is purely a flag, indicating the start or completion of an event, or group of events.
Hope this helps.
Jackie Gilliland
Member for
19 years 11 months
Member for19 years11 months
Submitted by yousif alaubidi on Tue, 2005-11-22 07:16
In primavera p3 ,you can set an activites as a Milestones when that activites work have an duration equel to zero in addation Milestones be a start date with out finsh date, and you can combine with Successsors and presdecessors
Member for
14 years 3 monthsHi Mike, thanks and advice
Hi Mike, thanks and advice noted.
Member for
19 years 10 monthsHi Abdulhaviz Welcome to
Hi Abdulhaviz
Welcome to Planning Planet.
A few hints onthe forum etiquette.
1. Do not wake up a long dead thread.
2. Do not add an answer to a thread that has already been adequately covered.
Best regards
Mike testro - Moderator
Member for
14 years 3 monthsFabio,I also think a
Fabio,
I also think a difference is that Milestones can be constrained while Flags cant. Cheers.
Member for
20 years 7 monthsRE: Milestones vs. Flags
Hi Fabrizio Capello
Shortly. flags are similar to milestones in that they are also zero duration activities and they flag either the start or completion of an activity or group of activities.
Flags however can only have a predecessor, but no successor activities and thus have no impact on your schedule. Flags do not need to be updated but are automatically completed when their predecessors are completed.
A flag is purely a flag, indicating the start or completion of an event, or group of events.
Hope this helps.
Jackie Gilliland
Member for
19 years 11 monthsRE: Milestones vs. Flags
Dear Fabrizio Capello
The differance as follows:
In primavera p3 ,you can set an activites as a Milestones when that activites work have an duration equel to zero in addation Milestones be a start date with out finsh date, and you can combine with Successsors and presdecessors
with regrds