Planners Member for 17 years 9 months Member for 17 years 9 months Submitted by Mohammad Mojah… on Thu, 2011-10-20 10:45 Permalink Dear You reply me or you Dear You reply me or you asked quetion Member for 14 years Member for 14 years Submitted by PLANNINGENGINEER1 on Thu, 2011-10-20 09:55 Permalink Q1wysiwyg_imageupload:: Q1[[wysiwyg_imageupload::height=422,width=291]] I DID'T GIVE ANY DURATION SO HOW PRIMAVERA ASSING THE DURATION? Q2 DIFFERENCE BETWEEN START & FINISH IS 4 WHILE IT SHOWING DURATION 9 Q3 ALSO HOW IT CALCULATE THE TOTAL FLOAT Q4 IS MY ASSINGING OF RELATION BETWEEN THE ACTIVITY IS CORRECT OR WRONG Q5 WHAT IS THE BEST WAY TO ASSING RELATION SHIP BETWEEN ACTIVITIES. Q6 IF I WANT TO MAKE THE ACTIVITY A1112 CRITAICAL SO WHAT I DO FOR THAT PURPOSE? Q7 WHAT IS EASIEST WAY TO DRAW THE CRITICAL PATH IN PRIMAVERA 6? Q7 HOW THE STAR ASSOCIATED WITH DATES ARE REMOVED? Log in or register to post comments
Member for 17 years 9 months Member for 17 years 9 months Submitted by Mohammad Mojah… on Thu, 2011-10-20 10:45 Permalink Dear You reply me or you Dear You reply me or you asked quetion
Member for 14 years Member for 14 years Submitted by PLANNINGENGINEER1 on Thu, 2011-10-20 09:55 Permalink Q1wysiwyg_imageupload:: Q1[[wysiwyg_imageupload::height=422,width=291]] I DID'T GIVE ANY DURATION SO HOW PRIMAVERA ASSING THE DURATION? Q2 DIFFERENCE BETWEEN START & FINISH IS 4 WHILE IT SHOWING DURATION 9 Q3 ALSO HOW IT CALCULATE THE TOTAL FLOAT Q4 IS MY ASSINGING OF RELATION BETWEEN THE ACTIVITY IS CORRECT OR WRONG Q5 WHAT IS THE BEST WAY TO ASSING RELATION SHIP BETWEEN ACTIVITIES. Q6 IF I WANT TO MAKE THE ACTIVITY A1112 CRITAICAL SO WHAT I DO FOR THAT PURPOSE? Q7 WHAT IS EASIEST WAY TO DRAW THE CRITICAL PATH IN PRIMAVERA 6? Q7 HOW THE STAR ASSOCIATED WITH DATES ARE REMOVED?
Member for
17 years 9 monthsDear You reply me or you
Dear You reply me or you asked quetion
Member for
14 yearsQ1wysiwyg_imageupload::
Q1[[wysiwyg_imageupload::height=422,width=291]]
I DID'T GIVE ANY DURATION SO HOW PRIMAVERA ASSING THE DURATION?
Q2
DIFFERENCE BETWEEN START & FINISH IS 4 WHILE IT SHOWING DURATION 9
Q3
ALSO HOW IT CALCULATE THE TOTAL FLOAT
Q4
IS MY ASSINGING OF RELATION BETWEEN THE ACTIVITY IS CORRECT OR WRONG
Q5
WHAT IS THE BEST WAY TO ASSING RELATION SHIP BETWEEN ACTIVITIES.
Q6
IF I WANT TO MAKE THE ACTIVITY A1112 CRITAICAL SO WHAT I DO FOR THAT PURPOSE?
Q7
WHAT IS EASIEST WAY TO DRAW THE CRITICAL PATH IN PRIMAVERA 6?
Q7
HOW THE STAR ASSOCIATED WITH DATES ARE REMOVED?