Hi gentlemen, how about changing % complete to zero and removing actuals for multiple activities in P6? I tried global change however I was not able to find the right operation. Perhaps someone knows the trick. TIA
I did the same thing as I do in P3, unfortunately the same message appears "Cannot Set Status to Not Started if Activity Has Actuals". Is there something wrong in my settings or any options that I need to do just to clear this problem.
Thanks for your reply, but one thing bothered me is I have an activity that is 20% complete with an actual start of 01 oct as an example. When I update the following week I noticed that I made a mistake on the activity that was updated, so I want to change the percent complete to zero and remove the tick in the actual start but a message will appear "Cannot Set Status to Not Started if Activity Has Actuals". I never encounter this problem in P3.
Thanks
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Mon, 2011-10-10 08:51
Just to add you have to do this in the right order -eg if you try and uncheck the stated box with the finished one still checked, you would get an error saying something like "activity cannot have an actual finish without an actual start"
Uncheck your finsh, then any % completees / actual durations / actual resources, then the start date.
Also, double check the relationships to ensure doing this won't cause any OOS (out of equence) working
Member for
22 years 5 months
Member for22 years5 months
Submitted by Roland Payawan on Mon, 2011-10-10 02:23
Member for
10 years 2 monthsHi,Quick and easy way to
Hi,
Quick and easy way to remove actuals using only 1 Global Change.
Check out my article here
https://www.linkedin.com/pulse/quick-way-remove-actuals-from-p6-schedule-one-go-using-azharuddin/?trackingId=kLitu4dDuCP3jndDcGzifQ%3D%3D
Member for
16 years 3 monthsmy posting includes 2 global
my posting includes 2 global changes
Member for
21 years 8 monthsI am not a P6 user but
I am not a P6 user but suggest you try either the Global Change approach or the Export/Import approach as per following link.
http://simplexgroup.com/dates-and-durations-in-oracle-primavera-p6/
Also make sure you verify the durations as they migh have been changed after updatings.
Good Luck
Member for
16 years 3 monthsHow to de-status a schedule1.
Member for
13 years 2 monthsHi all...is there any short
Hi all...
is there any short cut to change all activity 'completed' to 'not started'?
Regards
Member for
16 years 3 monthshere is a link to the
here is a link to the detailed instructions on how to do this
http://pmsite.com/forums/viewthread/3064/
Member for
13 years 11 monthsuse following;When activity
use following;
When activity Status is not equal to not started
Then;
Actual labour units equal to zero
Actual non labour unit equal to zero
activity status equa to not started.
Always keep a copy of your origional project before applying the global change because it can not be undone.
Regards;
Member for
14 years 4 monthsHi SM PUM, yes it will take
Hi SM PUM, yes it will take years to remove actuals of thousands activities. What operation in global change should be done then?
Member for
13 years 11 monthsFor Removing Actual you will
For Removing Actual you will have to apply global change.Removing actuals one by one will be waste of time
Member for
14 years 4 monthsHi gentlemen, how about
Hi gentlemen, how about changing % complete to zero and removing actuals for multiple activities in P6? I tried global change however I was not able to find the right operation. Perhaps someone knows the trick. TIA
Member for
14 years 3 monthsZhang Ting, Thanks a lot.
Zhang Ting,
Thanks a lot. Problem solved.
Henry
Member for
14 years 2 monthsFirst convert % complete to
First convert % complete to zero,and then change tick off “started”
Member for
14 years 3 monthsHi Roland, I did the same
Hi Roland,
I did the same thing as I do in P3, unfortunately the same message appears "Cannot Set Status to Not Started if Activity Has Actuals". Is there something wrong in my settings or any options that I need to do just to clear this problem.
Thanks
Member for
14 years 3 monthsGary, Thanks for your reply,
Gary,
Thanks for your reply, but one thing bothered me is I have an activity that is 20% complete with an actual start of 01 oct as an example. When I update the following week I noticed that I made a mistake on the activity that was updated, so I want to change the percent complete to zero and remove the tick in the actual start but a message will appear "Cannot Set Status to Not Started if Activity Has Actuals". I never encounter this problem in P3.
Thanks
Member for
16 years 7 monthsJust to add you have to do
Just to add you have to do this in the right order -eg if you try and uncheck the stated box with the finished one still checked, you would get an error saying something like "activity cannot have an actual finish without an actual start"
Uncheck your finsh, then any % completees / actual durations / actual resources, then the start date.
Also, double check the relationships to ensure doing this won't cause any OOS (out of equence) working
Member for
22 years 5 monthsHi Henry, Just go to the
Hi Henry,
Just go to the activity status, untick the STARTED and FINISHED date and put the Percent (%) back to zero and there you go.
Hope this wull do.
Cheers,