Basically i know the concept of that,but i want to know will there any change in the original duration by keeping the activity as resource dependent & if we want to level the resources what affect it will show in project completion?
Because in the above example you said like as per the task dependent the activity will work on mon-fri but resource will be off on wed.. so on which basis the activity will calculate the original duration?
Member for
21 years 10 months
Member for21 years10 months
Submitted by moutaz aldeib on Wed, 2011-09-28 18:53
In resource dependent, why Sat and Sun. are considered off days, this means the program will consider 3 days off (Wed. for the resource and two days for the task), is it logic?
Regards,
Moutaz
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Tue, 2011-09-27 18:39
Member for
15 years 8 monthsHi,I wrote an article to
Hi,
I wrote an article to explain What is the difference between Activity type: Task Dependent and Resource Dependent in Primavera P6.
You can read it here : https://doduykhuong.com/2018/03/15/what-is-the-difference-between-activity-type-task-dependent-and-resource-dependent-in-primavera-p6/
Regards
Member for
14 years 11 monthsHello Alex, Thanks for your
Hello Alex,
Thanks for your respond..
Basically i know the concept of that,but i want to know will there any change in the original duration by keeping the activity as resource dependent & if we want to level the resources what affect it will show in project completion?
Because in the above example you said like as per the task dependent the activity will work on mon-fri but resource will be off on wed.. so on which basis the activity will calculate the original duration?
Member for
21 years 10 monthsDear Alexandre, In resource
Dear Alexandre,
In resource dependent, why Sat and Sun. are considered off days, this means the program will consider 3 days off (Wed. for the resource and two days for the task), is it logic?
Regards,
Moutaz
Member for
22 years 9 monthsHello,a task dependent
Hello,
a task dependent activity will be scheduled accoring to its own calendar, a resource dependent activity according to the resource calendar
let's say you have a 5 day task starting Monday; the task calendar say the week is standard, 5 day workweek
you the assign a resource working 5 days, whose calendar says she's not working on Wednesdays
a) the task dependent activity will be scheduled Mon - Fri, and the resource will work on Wed
b) a resource dependent activity will start on Mon, be off on Wed, and finish the second Mon at night to let the resource accomplish her 5 day work
Hope this helps,
Alexandre