Primavera Project Planner - P3 Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2011-09-19 10:55 Permalink Hi Num Constraints should Hi Num Constraints should never be used to demonstrate a delay to the works. The first thing to do is remove ALL constraints and reschedule so that you have a reasonably realistic critical path. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2011-09-19 10:55 Permalink Hi Num Constraints should Hi Num Constraints should never be used to demonstrate a delay to the works. The first thing to do is remove ALL constraints and reschedule so that you have a reasonably realistic critical path. Best regards Mike Testro
Member for
19 years 10 monthsHi Num Constraints should
Hi Num
Constraints should never be used to demonstrate a delay to the works.
The first thing to do is remove ALL constraints and reschedule so that you have a reasonably realistic critical path.
Best regards
Mike Testro