If you create a Group Programme and copy all your individual programmes into the group you will then be able to use the file 3007_200252492644_ProjectMod.xls or 3007_200252492644_Project.xls to modify all your codes, resources, wbs etc. These files are available as a download file on the Primavera Website. If you use the Primavera Knowlegebase search tool it is quite easy to find and even easier to use.
Regards
Graham
Member for
21 years 1 month
Member for21 years2 months
Submitted by Jaco Stadler on Tue, 2004-12-28 00:52
I can live with duplication because I can make sure there are no duplicates before I import, but my question is, is it possible to export Code values and Code Value "DESCRIPTIONS" in the first place.
I have come across PRMBATCH which says I have to create a batch input file before I do the batch processing. How do I create a batch input file from an existing project?
Member for
22 years 4 months
Member for22 years4 months
Submitted by Shahzad Munawar on Mon, 2004-12-27 04:17
mkts option to import data to Excel and then export from Excel to form a Master schedule is not workable 100% . Duplication may be get in such procedure. So we should opt/follow that path through which such duplication may be avoided.
Have any idea to overcome the above situation !!!
Member for
22 years 6 months
Member for22 years6 months
Submitted by Rajeev Kumar on Mon, 2004-12-27 02:43
When I checked the export dialog box, I found no field for Code descriptions. i can only export and import code values and that too if they are assigned to activities only.
Is there any other way to export code values & descriptions and import them back?
Member for
22 years 1 monthRE: join projects
If you create a Group Programme and copy all your individual programmes into the group you will then be able to use the file 3007_200252492644_ProjectMod.xls or 3007_200252492644_Project.xls to modify all your codes, resources, wbs etc. These files are available as a download file on the Primavera Website. If you use the Primavera Knowlegebase search tool it is quite easy to find and even easier to use.
Regards
Graham
Member for
21 years 1 monthRE: join projects
Yes
You use a P 3 Excell Documents
CD:RaSamplesExcell You need to download these from the P3 CD.
You then use the file Project.
Cheers
Member for
22 years 6 monthsRE: join projects
I can live with duplication because I can make sure there are no duplicates before I import, but my question is, is it possible to export Code values and Code Value "DESCRIPTIONS" in the first place.
I have come across PRMBATCH which says I have to create a batch input file before I do the batch processing. How do I create a batch input file from an existing project?
Member for
22 years 4 monthsRE: join projects
mkts option to import data to Excel and then export from Excel to form a Master schedule is not workable 100% . Duplication may be get in such procedure. So we should opt/follow that path through which such duplication may be avoided.
Have any idea to overcome the above situation !!!
Member for
22 years 6 monthsRE: join projects
Thanks.
Can you tell me what "RA" stands for?
When I checked the export dialog box, I found no field for Code descriptions. i can only export and import code values and that too if they are assigned to activities only.
Is there any other way to export code values & descriptions and import them back?
Member for
23 years 8 monthsRE: join projects
Use RA can do it.
Export the dictionaries from P3 to Excel or Access or etc, then import it to the Master. Remember to check any duplication before import.