I suggest you create a View, Table and Filter (if required) all with the same name and use them together and adjust them in the same way as one would adjust a Layout in P3.
Unfortunately MSP does not give you the option of saving changes to a View in the same way as P3 so any change to a View is written to the database as soon as it is made. You will find this very frustrating, like many other things in MSP after coming from P3.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
Ref your problem with tasks being linked automatically, use
Tools->Options->Schedule(Tab), then ensure that the option titled "Autolink inserted or moved tasks" is unchecked. This can then be set as your default.
Regards,
Tony
Member for
22 years 7 months
Member for22 years7 months
Submitted by Dayanidhi Dhandapany on Sat, 2004-12-18 10:35
Member for
24 years 6 monthsRE: Saving Layouts
I suggest you create a View, Table and Filter (if required) all with the same name and use them together and adjust them in the same way as one would adjust a Layout in P3.
Unfortunately MSP does not give you the option of saving changes to a View in the same way as P3 so any change to a View is written to the database as soon as it is made. You will find this very frustrating, like many other things in MSP after coming from P3.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
Member for
21 years 3 monthsRE: Saving Layouts
Philip,
you can use different views to costomise the layout(As in P3. Follow Dayas suggestion to create views as per your need.
Member for
22 years 11 monthsRE: Saving Layouts
Hi Phillip,
Ref your problem with tasks being linked automatically, use
Tools->Options->Schedule(Tab), then ensure that the option titled "Autolink inserted or moved tasks" is unchecked. This can then be set as your default.
Regards,
Tony
Member for
22 years 7 monthsRE: Saving Layouts
Hello Philip,
I hope the following may help you:
1. Click View->More Views->New View or copy existing layout view and do some modifications to suit to your requirements.
2. Tools->Options->Calculation(Tab)->Set calculation mode to Manual(instead of Automatic)
Cheers!!!
Daya