Loading resources in Microsoft Project

Member for

14 years 10 months

Trevor,

After you resource load, How do you populate the manhour graph by either "tasks" or "roles". Please advise?

Member for

21 years 1 month

Yes, Rohit

Member for

17 years 6 months

Hi

If I have to allocate a gang of 75 carpenters for the entire project, should I enter 7500% in the max units column in the resource sheet and later as per the quantum of work in the task and duration I enter the required carpenters for them?

Is this correct?

 

Rohit

Member for

19 years 11 months

There are several ways, some of which are not recommended.

This one is good:

Go to the Resource Sheet View and create and define them first.

Then go to the Gantt Chart View, select a task and use the assign resources icon/button on the toolbar to show the Assign Resources dialog... etc.