Thank you so much for the help. I did try it and was content with the results. However when i go to the Task Usage i see the various resources underneath, and then if i update lets say 14 hours of actual on a particular day, then all the other resources for the same day get updated for the same amount too. Although i can go back and delete it from the other days, but why do all the other resources get updated even for the other days.
Ill could send you a scehdule that i had sampled, to practise this work update.
Regards,
Abdullah.
Member for
15 years 8 months
Member for15 years8 months
Submitted by Ismet Kocaman on Mon, 2011-07-04 23:47
In Project, Overtime work is part of the Total work. That means Work = Regular Work + Overtime Work. If there is no Overtime work then Work is equal to Regular work. Overtime work is the work outside of the resource calendar.
To complete the 8-hour duration task you can enter 8 hrs for Actual Work and then 2 hrs for Actual Overtime Work. Project will then calculate Actual Work (= 10 hrs) and Regular Work (=8 hrs). You can of course add these detail fields (Actual Work, Actual Overtime Work, Regular Work) to the timephased part of a Resource Usage view. The Actual Cost will be calculated as follows:
Member for
13 years 5 monthsHow to enter in Primavera
How to enter in Primavera p6...
Member for
13 years 5 monthsi'm having confussion where
i'm having confussion where to enter in resource usage sheet
Please clarify..
Member for
14 years 11 monthsHi Ismet, Thank you so much
Hi Ismet,
Thank you so much for the help. I did try it and was content with the results. However when i go to the Task Usage i see the various resources underneath, and then if i update lets say 14 hours of actual on a particular day, then all the other resources for the same day get updated for the same amount too. Although i can go back and delete it from the other days, but why do all the other resources get updated even for the other days.
Ill could send you a scehdule that i had sampled, to practise this work update.
Regards,
Abdullah.
Member for
15 years 8 monthsIn Project, Overtime work is
In Project, Overtime work is part of the Total work. That means Work = Regular Work + Overtime Work. If there is no Overtime work then Work is equal to Regular work. Overtime work is the work outside of the resource calendar.
To complete the 8-hour duration task you can enter 8 hrs for Actual Work and then 2 hrs for Actual Overtime Work. Project will then calculate Actual Work (= 10 hrs) and Regular Work (=8 hrs). You can of course add these detail fields (Actual Work, Actual Overtime Work, Regular Work) to the timephased part of a Resource Usage view. The Actual Cost will be calculated as follows:
Assuming Hours Per Day setting is 8 hours;
Actual Cost = 300 Rs/d * 1d + 90 Rs/h * 2hrs = 480 Rs
I hope this is what you are looking for. Pls give us feedback on your progress.
--Ismet