Mike,

 

Many thanks I'll find out what version Iv'e got and proceed as you suggest..

 

Thanks again.

 

Duncan

Member for

19 years 10 months

Hi Duncan

First you need to upgrade the easy plan to v 11 - easy plan does not show criticality so is useless for delay analysis.

The other thing is that if you have both easyplan and v 11 on the same computer they will

corrupt each other so you will nee to put the easy plan on a data stick.

If you can save the easyplan as an XER file you should then be able to open it in either PowerProject or P6.

When you have it as v 11 then you can create a baseline of the original programme using the File - Baseline Manager.

You can then create an as built baseline using the method described in the other thread.

Both baselines can be in the open view together - in fact I think the upper limit is 9 baselines in one view.

You can now impact your events on the live tasks.

Best regards

Mike Testro