3. Dialog box will appear go to the Level – Choose Split.
4. Shift+F9 ( Tools-Level)
5. Click splitting to open the Resource Splitting, Stretching and Crunching dialog box verify the project wide settings regarding the maximum number and duration of splits to allow per activity and the minimum allowable duration of a work chunk.
6. Level the Project.
Through this procedure you can split the resources. Please try it if you can successful.
Member for
16 years 1 monthDear Mike and GT, Please
Dear Mike and GT,
Please follow the following steps
To see this option adjust time scale from year/months to Months / week etc.
I think it will work. It is useful for P6.
if not please send me ur email address I will send u the Screen shot.
Thanks and regards,
Ranjit
Member for
19 years 10 monthsHi Ranjit How does this work
Hi Ranjit
How does this work if there are no resources - and does it create a physical split in the bar that you can add logic to?
Best regards
Mike Testro
Member for
16 years 1 monthHi GT, Please try the
Hi GT,
Please try the following steps
Split Activity
1. Select Activity
2. Ctrl+I (or View –Activity Detail- Contraints)
3. Dialog box will appear go to the Level – Choose Split.
4. Shift+F9 ( Tools-Level)
5. Click splitting to open the Resource Splitting, Stretching and Crunching dialog box verify the project wide settings regarding the maximum number and duration of splits to allow per activity and the minimum allowable duration of a work chunk.
6. Level the Project.
Through this procedure you can split the resources. Please try it if you can successful.
Best Regards,
Ranjit Kumar.
Member for
19 years 10 monthsHi G T I dont think you can
Hi G T
I dont think you can in P3 or in P6 for that matter.
Try converting your programme into MSP - split the tasks and then reconvert and see what happens.
Best regards
Mike Testro