I think it largely depends on how and why you are measuring progress.
If, for example, you are using Earned Value and presenting the client with a actual / forecast vs planned curve, the client might expect the total Earned Value at completion to equal the contract price, in which case indirects should be included.
If you are tracking productivity in terms of earned value vs actual cost, it might be useful to include indirects in order to highlight any issues with inefficient QA processes, for example.
But if you're just measuring site progress to aid site project management, I would ignore indirects.
Member for
24 years
Member for24 years1 month
Submitted by Daniel Limson on Wed, 2011-05-18 05:10
There are some construction projects where enabling and temporary works are measured as part of the progress, however, in your case, this is the first time i heard about such thing. I think it is not a common practice in construction and the progress calculation becomes more cumbersome, however, the way I would do it is a prorata with the permenent works involved so basically you just need to measure permanent works completed.
Member for
16 years 7 monthsI think it largely depends on
I think it largely depends on how and why you are measuring progress.
If, for example, you are using Earned Value and presenting the client with a actual / forecast vs planned curve, the client might expect the total Earned Value at completion to equal the contract price, in which case indirects should be included.
If you are tracking productivity in terms of earned value vs actual cost, it might be useful to include indirects in order to highlight any issues with inefficient QA processes, for example.
But if you're just measuring site progress to aid site project management, I would ignore indirects.
Member for
24 yearsHi Jiso, There are some
Hi Jiso,
There are some construction projects where enabling and temporary works are measured as part of the progress, however, in your case, this is the first time i heard about such thing. I think it is not a common practice in construction and the progress calculation becomes more cumbersome, however, the way I would do it is a prorata with the permenent works involved so basically you just need to measure permanent works completed.
Regards,
Daniel