Hi All,

I have a difficult situation here. Need help.

I am preparing a Baseline Schedule.

1) I have set up resource dictionary with Price/Unit, Units/Time and all other required data for each and every resources.

2) Then, I have assigned these resources to a particular activity. Say activity A.

3) Now, in the activity details -> Resource tab, I am not able to see Price/Unit & Budgetted Cost.

Why? Did I miss anything here?

Please helpout.

Thanks in advance.