Is it possible to use two planning units in P3 (i.e. Day & Unit in same Plan)

Member for

14 years 6 months

@ Patel...thanks for comments / my collegue is just a beginner level.

@ Andy.. thansk for the tip but it is not much clear to me.

Member for

20 years

Zahid,

We cannot use two units in one plan either in P3 or P6. please share with us if your collegue is more instrumental in this technique.

Jignesh Patel

Member for

20 years

Zahid,

We cannot use two units in one plan either in P3 or P6. please share with us if your collegue is more instrumental in this technique.

Jignesh Patel

Member for

19 years 2 months

Zahid

You set your units in user preferences, this only sets how units are displayed, you can only display one type of units at once BUT you can still set it to display as days but enter hours or vice versa (just remember to put the h after the number of units for hours and d for days).

Andy

Member for

14 years 6 months

Hi Alexandre

Thanks Indeed for reply.....but in P6 also it is not possible ?? as P6 gives more option if compare to P3 ...

 

Best regards,

Member for

22 years 9 months

Zahid,

no, its is 100% not possible to use 2 planning units in the same project plan; you have to define the unique planning unit for the project plan when you initialize the project (File, New), and you cannot work a different way

Alexandre