I need a help to find the scope of of work for civil work in construction phase in underground railway project.

the project is located in a modern and busy city.

Which methodology that I have to use cut and cover method or tunneling?

I wish you are wiling to share your data which inform the civil scope of work systematically.

 

Thank you

Best Regards

W.Yousman.

Member for

24 years

Hi Winner,

Trackwork construction may include the following

1.) Upstand or walkway (In tunnels)  This can be done very quickly if you have a prefabricated shutter. (48 to 60 meters / day)

2.) Trackwork Installation - This works includes Flush Butt Welding of long welded Rail (LWR), Distribution of Materials, which includes precast concrete slab (where rails are mounted and fastened) and concreting. Gauge and alignment check prior to concreting.  

Production rates for flush butt welding up to 30 FBW / machine / day  Equipment - Flush Butt Welding Machine

Distriution of Material - Gantry Crane on Wheel or Forklift

Guage and Alignment Checking Equipment, Concrete pump.

3.) Overhead Lines (OHL) if electric driven

 

Best regards,