Option ALAP in MSP is simmilar to ZFFC in P3 so valuable for You of course. But other interesting option is setting the finish date of project (instead of traditional start date project - in MSP we have only start OR only finish...). In this case MSP assume that all tasks are ALAP automatically. Meybe this way is valuable too. If You change finish date for start date you can revert (!) it for standard ASAP schedule. It is practical way in some cases, I suppose.
Good Luck
Member for
24 years 9 months
Member for24 years9 months
Submitted by Vladimir Liberzon on Sat, 2004-12-04 04:04
It may be used for the initial planning. But the schedule will change during project execution and these additional constraints being artificial will influence future schedules.
If you assign the task constraint ALAP then total slack as well as free float become zero, but if insert a column of free slack and then put another constraint FNET to make free slack zero.eg if task is showing 2 days free slack with current task finish date then you put FNET 2 days later then your free slack will become zero.
Member for
20 years 10 monthsRE: Free Slack
Option ALAP in MSP is simmilar to ZFFC in P3 so valuable for You of course. But other interesting option is setting the finish date of project (instead of traditional start date project - in MSP we have only start OR only finish...). In this case MSP assume that all tasks are ALAP automatically. Meybe this way is valuable too. If You change finish date for start date you can revert (!) it for standard ASAP schedule. It is practical way in some cases, I suppose.
Good Luck
Member for
24 years 9 monthsRE: Free Slack
It may be used for the initial planning. But the schedule will change during project execution and these additional constraints being artificial will influence future schedules.
Member for
21 years 3 monthsRE: Free Slack
If you assign the task constraint ALAP then total slack as well as free float become zero, but if insert a column of free slack and then put another constraint FNET to make free slack zero.eg if task is showing 2 days free slack with current task finish date then you put FNET 2 days later then your free slack will become zero.
Member for
24 years 6 monthsRE: Free Slack
As you have correctly alluded to setting a task in MSP to ALAP consumes all Total Float and not Free Float as in Primavera software.
I have not found a solution.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au