You can get the first three sections and the last section from the BOQs and the Issued for Construction Drawings. On the other hand, the Construction depends on the construction team.
For a Road Construction project, I assume that you need to site with your construction team and divide the project into zones and work on them according to priority. Once you have done that the activities generally are:
1. Site Survey.
2. Cut and fill
3. Civil Works according to the cross section of the road that you have; layer 1, 2, 3, etc. You will need to notive the MEP work included inside the civil works and sequence it accordingly.
4. Isolate the concrete structures (box culverts, bridges, etc) and have them in a separte category.
5. You might have side walks, paint, signals, etc after the end of construction. You will have to reveiw the BOQ and Plan them accordingly.
I hope that the information helps a little. If you be more specific and describe the project more, we can assist more.
Member for
19 years 2 monthsDear All, the main activities
Dear All,
the main activities for the raods ad infrastructure are cotaining but ot limited to the followig
prjoject commencemet date
Mobilisation
settig out and survey works
obtaiig costructio NOCs from all concerned authortities
trial trenches and varification of the existing services(utiliyies) location
protectio or relocation of existig utilities - as required
layig of ew utilities
submit shop drawings for road works
approval of shop drwings
submit the subcotractors for approval
approval of subcontractors
sumit materials submittals for approval
approva materials submittals
procurement of the matirals
earth works (cut and fill)
prepare the formatio layer
layig of subbase layer
layig of road base layer
spray betuminous prim coat
laying of ashpalt base course
spary tack coat
layig of asphalt weraring course
roads marking
errectig traffic sigs
general site cleaning and prepare the project for handingover
hand over the project.
Member for
19 years 10 monthsHi Raheel Primavera is noit
Hi Raheel
Primavera is noit the best software for linear projects - you should be considering Tilos or Vicos.
Best regards
Mike Testro
Member for
17 years 3 monthsDear Rahel, The major
Dear Rahel,
The major activities in most projects are
Shop Drawings and Approval
Material Submittals and Approval
Procurement
Construction
Testing and Commissioning and Handing Over.
You can get the first three sections and the last section from the BOQs and the Issued for Construction Drawings. On the other hand, the Construction depends on the construction team.
For a Road Construction project, I assume that you need to site with your construction team and divide the project into zones and work on them according to priority. Once you have done that the activities generally are:
1. Site Survey.
2. Cut and fill
3. Civil Works according to the cross section of the road that you have; layer 1, 2, 3, etc. You will need to notive the MEP work included inside the civil works and sequence it accordingly.
4. Isolate the concrete structures (box culverts, bridges, etc) and have them in a separte category.
5. You might have side walks, paint, signals, etc after the end of construction. You will have to reveiw the BOQ and Plan them accordingly.
I hope that the information helps a little. If you be more specific and describe the project more, we can assist more.
With kind regards,
Samer