Suggest you go into the resource calandar and create a Cost only activity bring up the following Columns 1. Auto Compute Actuals (needs a tick in the box); & 2. Calculate Costs from Units (box needs to be blank (no tick)).
Back in the bar chart section go to the resources and change budgetted units to zero.
Is this the same Cartherine that was on the SWIM (Stockport) job, with Phil & Crew?
Member for
15 yearsHi Catherine Suggest you go
Hi Catherine
Suggest you go into the resource calandar and create a Cost only activity bring up the following Columns 1. Auto Compute Actuals (needs a tick in the box); & 2. Calculate Costs from Units (box needs to be blank (no tick)).
Back in the bar chart section go to the resources and change budgetted units to zero.
Is this the same Cartherine that was on the SWIM (Stockport) job, with Phil & Crew?
Best Regards
James