THanks. Are u saying its not good practise to extract different schedule(differnet project) in the same folder. If I got u rightly, only updates or revision of the same schedules should be etracted in the same folder
Cheers
Bobo
Member for
22 years 9 months
Member for22 years9 months
Submitted by Alexandre Faul… on Thu, 2010-10-14 19:10
if the P3 schedule contained in the PRX file is a newer version of the one in the P3 folder, the obvious thing to do is to overwrite the older version; if not, you would better extract the PRX file in another folder
Member for
17 years 7 monthsAlex, THanks. Are u saying
Alex,
THanks. Are u saying its not good practise to extract different schedule(differnet project) in the same folder. If I got u rightly, only updates or revision of the same schedules should be etracted in the same folder
Cheers
Bobo
Member for
22 years 9 monthsBobo,if the P3 schedule
Bobo,
if the P3 schedule contained in the PRX file is a newer version of the one in the P3 folder, the obvious thing to do is to overwrite the older version; if not, you would better extract the PRX file in another folder
Alexandre