Export Activities and Resource quantities

Member for

22 years 9 months

Jhorbam,

the field Budgeted Quantity displays the total work amount for each activity, adding all the assigned resources together

you could try the tabular report RL-07 instead (Resources, Loading): you will see the individual work amount for each resource, organized by activity and detailed by day, week, ...

you can display this report in Primavera Look or save it with the .csv format and open it in Lotus 123, Excel

Alexandre