Duration Correlation of activities in a Risk Sched

Member for

20 years 11 months

Colin

No simple answer I’m afraid. There has to be some subjectivity. I usually start by running with correlation at 100% and at 0% (easy to do in pertmaster with a simple macro) - this gives an appreciation of the problem, whether it’s worth investment of time or not. Then I correlate similar sets of tasks (engineering, procurement etc), then I correlate across project for global factors (PM is the biggest driver).



Last (and most important) I see whether the results makes sense, then I show it to the stakeholders to ensure it is believable.

Member for

24 years 8 months

Colin,

activities that use the same resources have correlated durations. In our software Spider Project duration is calculated by dividing activity volume by resource productivity. Duration uncertainty is usually defined by resource productivity uncertainty.

This correlation is not single but most obvious.

Using Monte Carlo simulation you shall choose what to simulate though it will not work properly for large projects in any case.

Vladimir