There are many articles about the subject. What you described is only one opinion "Whoever use it first".
IMHO you need to look at it case by case. The Schedule is prepared by the Contractor. The client doesnt need the schedule, they need the end product. Schedules are tools to solve the issues. Expert opinion at site is a better way to solve the issues. Especially from the people who have hands on the issues.
With kind regards,
Samer
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Sun, 2010-07-18 16:31
It means the first delay events to occur will not result in EOT regardless of whether it is contractor or client responsibility, up until the point when all total float is eroded.
Member for
16 years 11 monthsRE: Total float issues
Thanks Samer and Gary
Member for
17 years 3 monthsRE: Total float issues
Dear Shahul,
There are many articles about the subject. What you described is only one opinion "Whoever use it first".
IMHO you need to look at it case by case. The Schedule is prepared by the Contractor. The client doesnt need the schedule, they need the end product. Schedules are tools to solve the issues. Expert opinion at site is a better way to solve the issues. Especially from the people who have hands on the issues.
With kind regards,
Samer
Member for
16 years 7 monthsRE: Total float issues
It means the first delay events to occur will not result in EOT regardless of whether it is contractor or client responsibility, up until the point when all total float is eroded.
Regards,
Gary