Data date will cover the purpose of Run date as you want to show in Legend in Printing

Member for

21 years 3 months

Dear Daya,

You can use the data date instead of run date. I know this not the true solution of your question but you can run the schedule on current date and then use data date.

Member for

22 years 10 months

There is no need to go to all of that trouble. The footer is fully customizeable. Just go to File / Page Setup / Footer. The Help file can help you for there. Good luck!

Member for

21 years 7 months

Hello Daya,

Probably this is not the best solution, but still you can try: i saved the schedule as a PDF file, and then deleted the time (Adobe Acrobat 5.0 has a ’touch up text tool’, which allows to make changes to the text)

hope it helps,

NJ