Hi Robert



Asta v 10 has a sort function that is on a hair trigger.



You may have inadvertantly sorted the tasks into date order or similar by double left clicking the column head.



Go to view> Sort> and tick Natural Order and it should come back into line.



Best regards



Mike Testro