Primavera Project Planner - P3 Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Thu, 2010-05-27 06:28 Permalink RE: Angel, The answer is "NO" because there is no month in between. Example of ordinal dates: If Project Start Date = Jul 2010 and Ordinal date set at Sep 2010 then: -2 Jul -1 Aug 1 Sep etc.. Log in or register to post comments
Member for 19 years Member for 19 years Submitted by Rodel Marasigan on Thu, 2010-05-27 06:28 Permalink RE: Angel, The answer is "NO" because there is no month in between. Example of ordinal dates: If Project Start Date = Jul 2010 and Ordinal date set at Sep 2010 then: -2 Jul -1 Aug 1 Sep etc..
Member for
19 yearsRE:
Angel,
The answer is "NO" because there is no month in between.
Example of ordinal dates:
If Project Start Date = Jul 2010 and Ordinal date set at Sep 2010 then:
-2 Jul
-1 Aug
1 Sep etc..