Dear Khalid Abdelaal,



Thank you for your reply. That link was very useful. More or less I used the method in my projects before.

In my last cost loading schedule for a construction project in South Carolina, I have used earned value analisys in P3. The Sub-Contractores were introduced as Resources and Project Billing Codes were introduced as Cost Accounts in P3. For each activity in the schedule I assigned the proper Sub-Contractors and Billing Codes by using of Resource Assignment method in P3.

Now Im able to create the Project Cash Flow Diagram (or S-Curve) and all monthly invoices prepare directly from P3.

Again thank you for your reply and keep in touch.

Ali

Member for

24 years 10 months

Dear Ali check the following link and reply



Presentation

make sure that you have acrobat reader



Khalid Abdelaal