Sorry! I wrote the status is in primavera - P3.1 Verson. whether is same changing on the default system of windows XP? I already try so doing but not change together with system of windows XP.
It is old software so the numeric system applies - you are lucky to get 2010 visible.
In Powerproject version 5 - some time ago - the date format was linked to the default windows set up but now you can set it to whatever configuration you want.
Member for
17 years 6 monthsRE: How can change the date display type in P3.
Hi Robin,
In P3, Click Format>Dates and only appeared the date format for Arabic numerals(21-3-2010), but not had that I need type (21-mar-2010)on months.
Member for
19 years 1 monthRE: How can change the date display type in P3.
In P3, Click Format>Dates and then Select the date format you want.
Member for
17 years 6 monthsRE: How can change the date display type in P3.
Hi Mike,
Sorry! I wrote the status is in primavera - P3.1 Verson. whether is same changing on the default system of windows XP? I already try so doing but not change together with system of windows XP.
Best regards
Mch714
Member for
19 years 10 monthsRE: How can change the date display type in P3.
Hi Mch
It is old software so the numeric system applies - you are lucky to get 2010 visible.
In Powerproject version 5 - some time ago - the date format was linked to the default windows set up but now you can set it to whatever configuration you want.
Best regards