You cannot in P3. You shall divide the activity. If the suspend is about dates only, you can create a specific calendar that the suspended days are not working.
But as a schedule and CPM point of view you should divide the activity.
Regards,
Safak VURAL
Member for
17 years
Member for17 years
Submitted by harzelli bouasria on Thu, 2010-02-11 04:32
Member for
17 years 5 monthsRE: Task Stand-by
Dear planners,
You cannot in P3. You shall divide the activity. If the suspend is about dates only, you can create a specific calendar that the suspended days are not working.
But as a schedule and CPM point of view you should divide the activity.
Regards,
Safak VURAL
Member for
17 yearsRE: Task Stand-by
hi shahul
it’s mean suspend and resume date, how we can put 2 on the same task in P3
Member for
16 years 11 monthsRE: Task Stand-by
Hi Harzelli
What does stand by mean? and With reference to which task are you referring