Primavera Project Planner - P3 Member for 22 years 11 months Member for 23 years Submitted by Steven Oliver on Fri, 2004-10-01 06:19 Permalink RE: Finish Flag Query Ooops. Having just reread my earlier post, Can I point out that a start flag can have a predecessor, but not a successor. Member for 22 years 2 months Member for 22 years 2 months Submitted by Samantha McCulloch on Fri, 2004-10-01 05:47 Permalink RE: Finish Flag Query Brilliant. Thank you for your quick reply. This absolutely makes sense. Good planning. Samantha Member for 22 years 11 months Member for 23 years Submitted by Steven Oliver on Fri, 2004-10-01 05:41 Permalink RE: Finish Flag Query Essentially, if a finish flag activity has no predecessors, then it will default to the latest early finish of the rest of the plan. Incidentally, a finish flag cannot have a successor (in the same way as a start flag cant have a predecessor. HTH Log in or register to post comments
Member for 22 years 11 months Member for 23 years Submitted by Steven Oliver on Fri, 2004-10-01 06:19 Permalink RE: Finish Flag Query Ooops. Having just reread my earlier post, Can I point out that a start flag can have a predecessor, but not a successor.
Member for 22 years 2 months Member for 22 years 2 months Submitted by Samantha McCulloch on Fri, 2004-10-01 05:47 Permalink RE: Finish Flag Query Brilliant. Thank you for your quick reply. This absolutely makes sense. Good planning. Samantha
Member for 22 years 11 months Member for 23 years Submitted by Steven Oliver on Fri, 2004-10-01 05:41 Permalink RE: Finish Flag Query Essentially, if a finish flag activity has no predecessors, then it will default to the latest early finish of the rest of the plan. Incidentally, a finish flag cannot have a successor (in the same way as a start flag cant have a predecessor. HTH
Member for
22 years 11 monthsRE: Finish Flag Query
Ooops. Having just reread my earlier post, Can I point out that a start flag can have a predecessor, but not a successor.
Member for
22 years 2 monthsRE: Finish Flag Query
Brilliant. Thank you for your quick reply.
This absolutely makes sense.
Good planning.
Samantha
Member for
22 years 11 monthsRE: Finish Flag Query
Essentially, if a finish flag activity has no predecessors, then it will default to the latest early finish of the rest of the plan.
Incidentally, a finish flag cannot have a successor (in the same way as a start flag cant have a predecessor.
HTH